what is charge type...

what is charge type in wip

such as wip move ,po move...

Charge type specifies how &

Charge type specifies how & when the resources 'll be charged for a job
 ex :  In case of wip move the resources 'll be charged when you move the PO
PO receipt is appllicable only for OSPs and it means resources 'll be charged when you receive the OSP PO

 what is move po and osp

 what is move po and osp

OSP - Out side processing In

OSP - Out side processing
In simple terms charge type specifies when the resources 'll be accounted

Just try understand the below flow

Raw material $5

work starts in dep 1 - resources charged $2 i.e the cost associated with the resources used in dep 1

work starts in dep 2 - resources charged $2 & new material used $1

Dep 3 - The finished good is complete but it needs to be painted which is done in another company- you send that FG to that company and receive it through a PO - Cost associated $5.
Now this cost 'll be accounted here for charge type PO receipt

Complete Job - Total cost $15